Jump Links

DEMOLITION, DISMANTLING, ASBESTOS REMOVAL, DIAMOND DRILLING & CUTTING, FAÇADE RETENTION AND RELATED SERVICES

Footbridge, M8 Motorway, Hillington

Pedestrian Footbridge, M8 Motorway, Hillington, Glasgow

 

CLIENT:

Graham Construction

 

LOCATION:

M8 Motorway

 

DATE COMMENCED:

14 July 2015

 

DURATION:

1 Night Shift [10 Hour Possession] for demolition/dismantling, with remaining works carried out normal working hours.

 

ACCIDENTS/INCIDENTS:

0

 

RECYCLE RATE:

98%

 

VALUE [INCL CREDITS]:

Circa £50,000

 

CONTRACT SPECIFICATION:

The scope of the works was the dismantling and removal of a pedestrian footbridge spanning the M8 Motorway. The bridge structure consisted of reinforced concrete piers, steel over-bridge. Steel parapets were present on each side of the bridge deck.

 

ACTIVITIES

Removal of footbridge decks by crane onto transport, haul off site

Hammer concrete column at base and lift to transport

Reduce base to 300 below ground level

Remove access stairs from ramp, both sides of bridge

 

Identified all known services, service lines near to the works and status of services and recorded in the Health & Safety File.

Client disconnected services and identified disconnection points prior to demolition.

Accepted service disconnection proof from relevant services companies and incorporated in Health & Safety Plan.

Inspected site for hazardous, contaminated or other materials found and reported findings to CDM Coordinator.

Proof given of Insurance to CDM Co-ordinator.

With full traffic management is in place, accessed both carriageways with cranes, protection, excavators, loaders and proceeded to set up as per lift plan

Accessed top of bridge with Brokk, fitted with hammer, and working from east bound side, working back across deck, broke slab at section ends to free for lifting and formed holes for chain placement

Accessed top of bridge deck and working under harness, cut handrails into section and folded back onto deck. Cut fixing bolts to ramp section and bridge sections to allow for lifting.

Positioned blocks of both cranes over lifts 1/2 lower chains and attached to lifts as per lift plan, took the strain, ensured lift free to raise from bridge.

By use of two way radios, proceeded with 1st lift, lowered to trombone trailer and hauled off site. Repeated for all other decks

With decks removed, positioned tracked demolition rigs adjacent to columns and formed hole through concrete column.   Positioned blocks over columns and attached chains and took strain

By tracked demolition rigs , broke along the bottom of columns to expose rebar.

With all rebar exposed, hot cut column free and loaded to transporter, hauled off site for recycling. Repeated for all columns

With columns removed, de-rigged and removed cranes from site

By tracked demolition rigs , reduced base of column to 300mm below ground level and excavated material from base

Manually hot cut steel flush and removed from excavation.

By low loader, removed all plant and material from motorway. Re-installed barriers and re-opened motorway to traffic.

By tracked demolition rigs located at bottom of stairway both sides, grubbed up stairs and hard standing, loaded to transport and hauled off site for recycling.

By tracked demolition rigs, infilled all voids and graded area of stair removal

Obtained Client approval to work completion

 

 

 


Professional memberships Demolition Contractors Association Accredited Site Audit Scheme - National Federation of Demolition Contractors Constructonline TUV ISO 9001, iSO 14001, BS OHSAS18001 Scottish Building Federation National Demolition Training Group (NDTG) Scottish Plant Owners Association (SPAO) Considerate Constructors Scheme Safecontractor Approved