Dunglass Bridge, Exxon, Dumbarton
Project Description
Client: Balfour Beatty
Duration: November 2026- 54hr disruptive
Bridge construction:
9 meter span pre-cast concrete beam bridge positioned overtop of railway, with brickwork parapets and concrete pilasters.
Scope of works:
pre disruptive works
track saw cutting and removal of 4no wing walls over Saturday night possessions leading up to disruptive
54 hr disruptive
Installation of track protection to railway to provide protection during the course of the works
track saw cutting and removal of 4no concrete pilasters
Mechanical demolition of bridge deck
processing and removal of material arising
removal of track protection
Coring of holes in abutment wall for dowels to install new bridge deck
Key Challenges
works were carried out during a 54 hr disruptive with works completed ahead of programme.
liaise with client and network rail to programme works
Demolition Methods
Mechanical demolition:
demolished utilising our PC390 and PC490 Komatsu demolition spec Excavators, breaking out concrete cover and infill of RC Beams then lifting out of beams to minimise material dropping g onto track protection
Diamond drilling and cutting:
Concrete cutting with utilising 2 of our DST 20-CA track saws, cutting the 4 wing walls of the bridge during Saturday nightshift possessions and cutting of the 4no concrete pilasters during the 54hr disruptive all cut down to level to allow installation of new bridge deck
Concrete drilling of 32no 100mm diameter 300-350mm deep holes in the concrete bridge abutments following demolition to allow the installation of dowels for new bridge
Achievements
No lost time
Works completed on programme
No Site complaints
collaboration between GBS and BB and Network rail allowed works to be planned and carried out on programme.
100% recycle rate
passed rail inspection and railway reopened on programme