Dunglass Bridge, Exxon, Dumbarton

Bridge Demolition in Scotland, Dumbarton, over top of railway
complete demolition of over rail bridge, showing cleared tracks in Scotland, uk

Project Description

Client: Balfour Beatty

Duration: November 2026- 54hr disruptive

Bridge construction:

9 meter span pre-cast concrete beam bridge positioned overtop of railway, with brickwork parapets and concrete pilasters.

Scope of works:

pre disruptive works

  • track saw cutting and removal of 4no wing walls over Saturday night possessions leading up to disruptive

    54 hr disruptive

  • Installation of track protection to railway to provide protection during the course of the works

  • track saw cutting and removal of 4no concrete pilasters

  • Mechanical demolition of bridge deck

  • processing and removal of material arising

  • removal of track protection

  • Coring of holes in abutment wall for dowels to install new bridge deck

Key Challenges

  • works were carried out during a 54 hr disruptive with works completed ahead of programme.

  • liaise with client and network rail to programme works

Demolition Methods

Mechanical demolition:

demolished utilising our PC390 and PC490 Komatsu demolition spec Excavators, breaking out concrete cover and infill of RC Beams then lifting out of beams to minimise material dropping g onto track protection

Diamond drilling and cutting:

Concrete cutting with utilising 2 of our DST 20-CA track saws, cutting the 4 wing walls of the bridge during Saturday nightshift possessions and cutting of the 4no concrete pilasters during the 54hr disruptive all cut down to level to allow installation of new bridge deck

Concrete drilling of 32no 100mm diameter 300-350mm deep holes in the concrete bridge abutments following demolition to allow the installation of dowels for new bridge

Achievements

  • No lost time

  • Works completed on programme

  • No Site complaints

  • collaboration between GBS and BB and Network rail allowed works to be planned and carried out on programme.

  • 100% recycle rate

  • passed rail inspection and railway reopened on programme